Levee has failed us – Rous to move part of levee upstream to improve its flood capacity

 Previous repair work undertaken by Rous to Bungawalbin Levee at the failure point.

A critical section of Bungawalbin Levee is going to be relocated to ensure its long term resilience during floods.

In 2024, Rous received grant of $6.9 million through the Natural Disaster Relief Assistance Program and State and Commonwealth Government’s Disaster Recovery Funding Arrangements to repair Bungawalbin Levee after the 2022 floods.

The Bungawalbin Levee is located between Woodburn and Coraki in the Richmond Valley Council area and is an 8km long earth levee that protects properties from minor and moderate floods.

The levee has failed twice, in 2017 and 2021, and sustained further damage in 2022 and 2025.

Following geotechnical investigations, environmental surveys and options assessment, the preferred option currently being considered by Rous involves relocating a critical section of the Bungawalbin Levee.

Rous Rural Flood Mitigation manager Chrisy Clay said the assessment recommended that the levee should no longer be located next to the creek bank because of the instability of the bank.

Failure of the Bungawalbin Levee following flooding in 2021 which overtopped the levee. Photos: Rous

“The current preferred option involves moving roughly 1.5km of the upstream section, so it becomes part of Bungawalbin–Whiporie Road.” she said.

Rous has been consulting with landowners on the preferred option before any final decisions are made, Ms Clay said.

Richmond Valley mayor and Rous chair Robert Mustow said the Bungawalbin Levee has “failed us over the past decade.”

“The current repair represents a once in a generation opportunity to build lasting resilience into the Bungawalbin Levee,” Mr Mustow said.

Subject to landowner feedback, detailed design and approvals, on-ground works are anticipated to begin this year and continue into early 2027.

This information was provided by Rous County Council.