Susanna Freymark
Work at the Airforce Beach carpark in Evans Head has been halted after artefacts were discovered.
Richmond Valley Council started construction on October 21 and work was expected to take six weeks.
In accordance with the requirements of the council’s Crown Land licence, a cultural monitor was present at the site as work began, a council report said.
During initial excavations, material of potential Aboriginal cultural heritage significance was identified within the beach access area.
More material was found and identified in the carpark area.
All work was stopped and the site secured in line with the project’s Review of Environmental Factors and Stop Work Procedure.
An inspection identified a grinding and chipping stone, shard material and shell midden.
The council notified the relevant organisations including Heritage NSW.
A compliance team from the NSW Biodiversity and Heritage Regulator is investigating. 
At the November 17 council meeting in Casino, councillor Robert Hayes asked if there was “any movement on the artefacts”.
Council’s director of infrastructure services & projects Ben Zeller said things were at “an absolute standstill”.
Works will not resume until the council receives advice and confirmation from Heritage NSW that construction can proceed.
The timeframe for the regulatory investigation is uncertain, and further cultural material may be present in the construction area.
The suspension of works will add additional costs through contractor delays and any further heritage assessment or approval requirements.
The project is costing $632,040 with funding of $392,040 from the Office of Local Government and $200,000 council contribution plus $40,000 from general revenue.